Site clearance
The process of site clearance is generally undertaken as part of enabling works, carried out to prepare a site for construction. It involves the clearing the site to allow other remedial, treatment or demolition works to take place before the actual construction works can begin.
It involves clearing a site of any machinery or equipment, unwanted surplus materials, rubbish, and so on. Site clearance may also involve clearing away vegetation and surface soil, and levelling and preparing the ground for the planned construction works. Care should be taken to ensure that there are the correct approvals in place, particularly for trees which may be protected.
A site waste management plan (SWMP) may be prepared before site clearance begins. This describes how materials will be managed efficiently and disposed of legally, explaining how the re-use and recycling of materials will be maximised. All types of waste present on the site must be removed safely and efficiently. If there is any contaminated waste or potentially hazardous substances (such as asbestos), professional disposal experts must be consulted to safely handle them.
For more information, see Site waste management plan.
Site clearance might be carried out as part of the main construction contract, or it may be carried out in advance of the main contract, and might be part of a wider contract including other enabling works or facilitating works, such as; demolition works, soil stabilisation works, services diversion, constructing access roads, and so on.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February
Comments